South Africa's Minister of Public Works and Infrastructure, Dean Macpherson, put it simply in a 24 November opinion piece: the country knows what it needs to build, and "the real challenge is delivery." He points to projects that are delayed, disrupted or never finished. He calls for better project preparation, stronger accountability, capable contractors and safer sites.
This week we turn that message into a practical checklist. It is for anyone commissioning a building or infrastructure project, whether you are a municipality, a provincial department, a school or hospital owner, or a private developer.
Why preparation matters now
There is a real pipeline of public work coming. Infrastructure South Africa (ISA) has released its third Construction Book, listing 110 projects worth about R395 billion. These projects have allocated budgets and are expected to enter procurement and construction over the next 12 to 18 months.
The book includes 16 social infrastructure projects worth R52 billion. It also includes ten municipal projects worth about R112 billion in places such as Polokwane, eThekwini, Johannesburg and Mogale City. ISA has also said it plans quarterly status reports on listed projects, to show whether they are proceeding as intended.
On the private side, Stats SA reported that the value of building plans passed from January to April 2026 rose 5.7% to R30.99 billion compared with the same period in 2025.
When more projects compete for the same consultants, contractors and materials, good preparation becomes more valuable. The work you do before tender shapes most of what happens on site.
Step 1: Define the need and test it
Start with a short, written brief. What problem does the project solve? Who will use it? What does success look like in five and in twenty years?
Then test the brief with a feasibility study. A good study compares options (refurbish, extend or build new), checks the site, sets a realistic budget range and identifies the main risks. It should end with a clear go or no-go decision.
Do not skip this to save time. A weak brief is a common reason for design changes after the contractor is appointed, and late changes are expensive.
Step 2: Know your site and your services
Before design starts, find out what is under and around the site:
- a land survey and confirmation of the title, servitudes and zoning
- a geotechnical investigation, so foundations are designed for real ground conditions
- the capacity of municipal water, sewer, stormwater, roads and electricity connections
Bulk services are often a hidden cost. If a connection needs upgrading, it can add months and money. Ask the municipality early and get the answers in writing.
Step 3: Map the approvals
List every approval the project needs and who gives it. Typical items include:
- land-use or rezoning approval
- environmental authorisation, where it is triggered
- building plan approval by the municipality under the National Building Regulations and SANS 10400
- NHBRC enrolment for new homes
Put these on the programme as real tasks with real durations. Approvals tackled late or in the wrong order can hold up the whole project.
Step 4: Cost it properly
Get an independent cost estimate from a quantity surveyor at each design stage, not only at tender. The estimate should show:
- construction cost, broken down by element
- professional fees and statutory costs
- escalation to the expected construction period
- a contingency that reflects how much is still unknown
Make sure the approved budget matches the estimate. If it does not, change the scope now rather than on site.
Step 5: Match the contractor to the job
The Minister notes that South Africa needs contractors with the technical expertise, experience, resources and financial capacity to take on projects of different sizes and complexity.
For owners, that means:
- set CIDB grading requirements that fit the value and class of work
- ask for evidence of similar completed projects and key staff
- look at financial capacity, not only price
- choose a procurement route and contract form (such as JBCC, or the form your organisation prescribes) that suit the project's risks, and keep the documents consistent
A complete, coordinated tender package reduces claims. Gaps in drawings or specifications usually come back as variations.
Step 6: Plan for site security and community engagement
The Minister also names construction site disruption and criminality as one of the most persistent threats to infrastructure delivery.
Plan for this before the contractor arrives. Budget for site security. Engage the local community and ward structures early. Explain the project and be clear about how local labour and subcontracting will work. Agree in the contract how stoppages will be reported and handled.
Step 7: Measure and report progress
ISA's plan to publish quarterly updates is a useful model for any owner. Set a baseline programme and budget at contract award. Then report monthly against it: progress, cost to date, forecast final cost, risks and decisions needed.
Regular, honest reporting lets you act while problems are still small. It also builds trust with councils, boards, funders and the public.
What to do next
If you have a project in your budget for the next 12 to 18 months, check where it stands against these seven steps. If the brief, site information, approvals path or cost plan is incomplete, fix that before you go to tender.
Our Development & feasibility team can help you test a project before you commit to it.
Sources
- Fixing infrastructure delivery: from plans to performance (Minister Dean Macpherson, 24 November 2026)
- ISA releases third construction book with R395bn infrastructure pipeline – Engineering News
- Infrastructure South Africa promises quarterly updates ahead of release of third edition of Construction Book – Engineering News
- Building plans and completions rise in first trimester, says Stats SA – Business Day